[doc] Added project dashboard help in English
This commit is contained in:
parent
0d7c44cd05
commit
a549306f7d
2 changed files with 198 additions and 0 deletions
163
doc/src/user/en/17-project-dashboard.rst
Normal file
163
doc/src/user/en/17-project-dashboard.rst
Normal file
|
|
@ -0,0 +1,163 @@
|
||||||
|
Project dashboard
|
||||||
|
#################
|
||||||
|
|
||||||
|
.. contents::
|
||||||
|
|
||||||
|
The project dashboard is a *LibrePlan* perspective which contains a set of **KPI (Key Performance Indicators)**
|
||||||
|
which help to know how is performing a project according to:
|
||||||
|
|
||||||
|
* how the work is progressing
|
||||||
|
* how much is costing
|
||||||
|
* the status of the resources allocated
|
||||||
|
* the time constraints
|
||||||
|
|
||||||
|
Progress performance indicators
|
||||||
|
===============================
|
||||||
|
|
||||||
|
There are two indicators calculated: project progress percentage and task
|
||||||
|
status.
|
||||||
|
|
||||||
|
Project progress percentage
|
||||||
|
---------------------------
|
||||||
|
|
||||||
|
It is a chart where the global progress of a project is calculated and compared to
|
||||||
|
the expected value of progress the project should have according to the *Gantt*.
|
||||||
|
|
||||||
|
The progress is represented with two bars:
|
||||||
|
|
||||||
|
* *Current progress*. It is the progress existing at the moment according to
|
||||||
|
the measurements done.
|
||||||
|
* *Expected progress*. It is the progress the project should have at the
|
||||||
|
moment according to the planning created.
|
||||||
|
|
||||||
|
The project global progress is estimated in several different ways as there
|
||||||
|
is not a unique right method to do it:
|
||||||
|
|
||||||
|
* **Spreading progress**. It is the progress type set as spreading progress
|
||||||
|
at project level. In this case, there is not way to calculate an expected
|
||||||
|
value and only the current bar is displayed.
|
||||||
|
* **By all tasks hours**. The progress of all project tasks is averaged to
|
||||||
|
calculate the global value. It is a weighted average taking into account
|
||||||
|
the number of hours allocated at each task.
|
||||||
|
* **By critical path hours**. The progress of the tasks belonging to any of
|
||||||
|
the critical paths of the project is averaged to obtain the global value.
|
||||||
|
It is done a weighted average taking into account the total allocated hours
|
||||||
|
of each of the involved tasks.
|
||||||
|
* **By critical path duration**. The progress of the tasks belonging to any of
|
||||||
|
the critical paths is averaged by doing a weighted average but this time taking
|
||||||
|
into account the duration of each involved task instead of the assigned
|
||||||
|
hours.
|
||||||
|
|
||||||
|
Task status
|
||||||
|
-----------
|
||||||
|
|
||||||
|
A pie chart showing the percentage of the project tasks being at different
|
||||||
|
states. The defined states are the next ones:
|
||||||
|
|
||||||
|
* **Finished**. They are the completed tasks, detected by a 100% progress value measured.
|
||||||
|
* **In progress**. They are the tasks which are underway. They have a
|
||||||
|
progress value distinct from 0% and 100% or some worked time tracked.
|
||||||
|
* **Ready to start**. They have a progress of 0%, do not have time tracked, all their *FINISH_TO_START* dependent tasks are *finished*
|
||||||
|
and all their *START_TO_START* dependent tasks are *finished* or *in progress*.
|
||||||
|
* **Blocked**. These are the tasks with a 0% of progress, without time
|
||||||
|
tracked and with previous dependent tasks neither *in progress* not in *ready to start* state.
|
||||||
|
|
||||||
|
Cost indicators
|
||||||
|
===============
|
||||||
|
|
||||||
|
There are several *Earned Value Management* cost indicators calculated:
|
||||||
|
|
||||||
|
* **CV (Cost Variance)**. Difference between the *Earned Value curve* and the
|
||||||
|
*Actual Cost curve* at the moment. Positive values indicate benefit and
|
||||||
|
negative ones loss.
|
||||||
|
* **ACWP (Actual Cost Work Performed)**. It is the total number of hours tracked in the project at the
|
||||||
|
moment.
|
||||||
|
* **CPI (Cost Performance Index)**. It is the *Earned Value / Actual
|
||||||
|
Cost* ratio.
|
||||||
|
|
||||||
|
* > 100 is good, means to be under budget.
|
||||||
|
* = 100 is also good, means the cost is right on plan.
|
||||||
|
* < 100 is bad, means that the cost of completing the work is higher than
|
||||||
|
planned.
|
||||||
|
|
||||||
|
* **ETC (Estimate To Complete)**. It is the time that is pending to devote
|
||||||
|
to the project to finish it.
|
||||||
|
* **BAC (Budget At Completion)**. It is the total amount of work allocated
|
||||||
|
in the project plan.
|
||||||
|
* **EAC (Estimate At Completion)**. It is the manager projection of the total
|
||||||
|
cost at project completion time according to the *CPI*.
|
||||||
|
* **VAC (Variance At Completion)**. It is the difference between the *BAC*
|
||||||
|
and the *ETC*.
|
||||||
|
|
||||||
|
* < 0 is over budget.
|
||||||
|
* > 0 is under budget.
|
||||||
|
|
||||||
|
Resources
|
||||||
|
=========
|
||||||
|
|
||||||
|
To analyze the project from resources' point of view two ratios and a histogram
|
||||||
|
are provided.
|
||||||
|
|
||||||
|
Estimation deviation on completed task histogram
|
||||||
|
------------------------------------------------
|
||||||
|
|
||||||
|
It is calculated the deviation between the number of hours allocated to the
|
||||||
|
project tasks and the eventual number of hours dedicated to them.
|
||||||
|
|
||||||
|
The deviation is calculated in percentage for all the finished tasks and the
|
||||||
|
calculated deviations are represented in a histogram. In the vertical axis the number of tasks which are in an
|
||||||
|
interval of deviation is shown. Six deviation intervals are dynamically calculated.
|
||||||
|
|
||||||
|
Overtime ratio
|
||||||
|
--------------
|
||||||
|
|
||||||
|
It sums up the overload of the resources that are allocated in the project tasks.
|
||||||
|
It is calculated according to the formula: **overtime ratio = overload / (load +
|
||||||
|
overload)**.
|
||||||
|
|
||||||
|
* = 0 is good, meaning that the resources are not overloaded.
|
||||||
|
* > 0 is bad, meaning that the resources are overloaded.
|
||||||
|
|
||||||
|
Availability ratio
|
||||||
|
-------------------
|
||||||
|
|
||||||
|
It sums up the capacity that is free in the resources currently allocated to the
|
||||||
|
project. Therefore it is a measurement of the resource availability to receive more allocations without
|
||||||
|
being overloaded. It is calculated as: **availability ratio = (1 - load/capacity)*100**
|
||||||
|
|
||||||
|
* Possible values are between 0% (fully assigned) and 100 (not assigned).
|
||||||
|
|
||||||
|
Time
|
||||||
|
====
|
||||||
|
|
||||||
|
They are included two charts: a histogram for the time deviation in the finish
|
||||||
|
time of project tasks and a pie chart for the deadline violations.
|
||||||
|
|
||||||
|
Task completion lead or lag
|
||||||
|
---------------------------
|
||||||
|
|
||||||
|
It is calculated the difference in days between the planned end time for the project
|
||||||
|
tasks and their actual end time. The planned completion date is got from the
|
||||||
|
*Gantt* and the actual finish date is got from the last time tracked at the task.
|
||||||
|
|
||||||
|
The lag or lead in task completion is represented in a histogram. In the
|
||||||
|
vertical axis the number of tasks with a lead/lag day difference value
|
||||||
|
corresponding to the abscissa days interval is represented. Six
|
||||||
|
dynamic task completion deviation intervals are calculated.
|
||||||
|
|
||||||
|
* Negative values mean finishing ahead of time.
|
||||||
|
* Positive values mean finishing with a delay.
|
||||||
|
|
||||||
|
Deadline violations
|
||||||
|
-------------------
|
||||||
|
|
||||||
|
On one hand it is calculated the margin with the project deadline, if set. On the other hand a pie chart with
|
||||||
|
the percentage of tasks hitting their deadline is painted. Three types of values
|
||||||
|
are included in the chart:
|
||||||
|
|
||||||
|
* Percentage of task without deadline configured.
|
||||||
|
* Percentage of ended tasks with an actual end date later than their
|
||||||
|
deadline. The actual end date is got from the last time tracked in the
|
||||||
|
task.
|
||||||
|
* Percentage of ended tasks with an actual end date sooner than their
|
||||||
|
|
||||||
35
doc/src/user/en/index.rst
Normal file
35
doc/src/user/en/index.rst
Normal file
|
|
@ -0,0 +1,35 @@
|
||||||
|
#############################
|
||||||
|
LibrePlan: User documentation
|
||||||
|
#############################
|
||||||
|
|
||||||
|
.. image:: images/logo.png
|
||||||
|
:align: left
|
||||||
|
|
||||||
|
Following document contains necessary help for using LibrePlan, the opensource web application for project planning.
|
||||||
|
|
||||||
|
This document is divided in three main sections:
|
||||||
|
|
||||||
|
First, global goals and behaviour.
|
||||||
|
|
||||||
|
Second, basic entities to understand the minimum concepts to use LibrePlan.
|
||||||
|
|
||||||
|
Finally, complete processes description to create orders, projects, project planning, resources assignment, advance assignment and result extraction.
|
||||||
|
|
||||||
|
#. `Introduction <01-introducion.html>`__
|
||||||
|
#. `Criteria <02-criterios.html>`__
|
||||||
|
#. `Calendars <03-calendarios.html>`__
|
||||||
|
#. `Progress <04-avances.html>`__
|
||||||
|
#. `Management of resources <05-recursos.html>`__
|
||||||
|
#. `Orders and order elements <06-pedidos.html>`__
|
||||||
|
#. `Task planning <07-planificacion.html>`__
|
||||||
|
#. `Assignment of resources <08-asignacion.html>`__
|
||||||
|
#. `Work reports <09-partes.html>`__
|
||||||
|
#. `Tags <10-etiquetas.html>`__
|
||||||
|
#. `Materials <11-materiales.html>`__
|
||||||
|
#. `Quality forms <12-formularios-calidad.html>`__
|
||||||
|
#. `Users <13-usuarios.html>`__
|
||||||
|
#. `Cost management <14-custos.html>`__
|
||||||
|
#. `Reports <15-informes.html>`__
|
||||||
|
#. `LDAP Configuration <16-ldap-authentication.html>`__
|
||||||
|
#. `Project dashboard <17-project-dashboard.html>`__
|
||||||
|
#. `About <20-acerca-de.html>`__
|
||||||
Loading…
Add table
Reference in a new issue