48 lines
1.7 KiB
ReStructuredText
48 lines
1.7 KiB
ReStructuredText
Reports
|
|
########
|
|
|
|
.. _informes:
|
|
.. contents::
|
|
|
|
|
|
Reports
|
|
=======
|
|
|
|
"NavalPlan" is integrated with *JasperReports* to manage reports, which allows users to enter various reports to analyse available data in the program.
|
|
|
|
The defined reports are:
|
|
|
|
* Order report. Showing a row for each order task. The fields shown for each task are:
|
|
|
|
* Code
|
|
* Name
|
|
* Estimated start date
|
|
* Date of first report
|
|
* Estimated finish date
|
|
* Date of last report
|
|
* *Deadline* date (if applicable)
|
|
* Progress percentage (the one marked as current).
|
|
* Current status: Finished, in progress, pending, blocked.
|
|
* *Deadline* status: Achieved, not achieved, and blank (if there is no deadline).
|
|
|
|
* Work summary report: This report summarises the hours worked according to the work reports.
|
|
* Report on the hours worked by workers or worker groups. This report shows a summary based on date and subtotal of worked hours per existing resource in the program.
|
|
* Project progress list report. A report that shows a row for each filtered order so that different types of progress selected can be viewed.
|
|
* Report listing the hours worked on a project. This provides information on the following parameters:
|
|
|
|
* Estimated hours (EH)
|
|
* Total planned hours (Total PH)
|
|
* Planned hours (PH)
|
|
* Real hours (RH)
|
|
* Average progress (AP)
|
|
* Assigned progress (AP)
|
|
* Planned progress (PP)
|
|
* Cost variation (CV)
|
|
* Schedule variation (SV)
|
|
* Cost performance index (CPI)
|
|
* Schedule performance index (SPI)
|
|
|
|
* Report on worked and assigned hours according to work types.
|
|
* Report on worked and assigned hours according to tags.
|
|
* Report on the cost of resources assigned to tasks based on hour types.
|
|
|