TASKPM/ganttzk
Óscar González Fernández f7e3adbfd2 Now more tasks are reachable from a TaskPoint
Now from an end date change the start can change because of backwards
scheduling. This must be considered when considering if a dependency
provokes an infinite loop or when calculating the recalculations to be
done.

For example, if a end date of a tasks is modified the start date could
be moved and this could provoke other tasks depending on this start
date to be moved. This is true for all tasks but the containers that
have a special behavior.

FEA: ItEr64OTS03PlanificacionHaciaAtras
2010-12-01 15:09:04 +01:00
..
src Now more tasks are reachable from a TaskPoint 2010-12-01 15:09:04 +01:00
pom.xml [Bug #712] Printed container as in critical path when it is collapsed and some of its children are in critical path. 2010-11-15 21:06:26 +01:00