Now from an end date change the start can change because of backwards scheduling. This must be considered when considering if a dependency provokes an infinite loop or when calculating the recalculations to be done. For example, if a end date of a tasks is modified the start date could be moved and this could provoke other tasks depending on this start date to be moved. This is true for all tasks but the containers that have a special behavior. FEA: ItEr64OTS03PlanificacionHaciaAtras |
||
|---|---|---|
| .. | ||