Lorenzo Tilve
db41b9a168
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: Fixed bug introduced regarding icon pressed padding
2010-02-12 11:15:47 +01:00
Lorenzo Tilve
ae5dab9070
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: Fixed bug related with weekend days not shown on orders without deadlines
2010-02-12 11:15:44 +01:00
Lorenzo Tilve
2f5c8577ba
ItEr47S08RFNavegacionOrganizacionTraballoItEr46S09: Shortened labels in order filters
2010-02-12 11:15:40 +01:00
Lorenzo Tilve
f1d2ce689d
ItEr47S08RFNavegacionOrganizacionTraballoItEr46S09: Added icon to reassign command
2010-02-12 11:15:37 +01:00
Susana Montes Pedreira
cd4a3d0564
ItEr47S08RFNavegacionOrganizacionTraballoItEr46S09 : Fixes a bug in the loading of the advances of the current order on demand.
2010-02-12 10:58:40 +01:00
Fernando Bellas Permuy
664d7a8f63
ItEr47S12CUImportacionRecursosProductivosItEr46S13: Added updating functionality to ResourceServiceREST
...
Updating functionality has been added to ResourceServiceREST. All data associated to a resource can be updated with the exception of the calendar field, since the updating semantics are only clearly defined for such field at this moment (what happens with the previous derived calendar: modified?, removed?, disabled?).
As part of this patch, some improvements to CriterionServiceREST implementation have also been made. In particular, updateUnvalidated methods has been added to related entities (as in ResourceServiceREST). Unlike createUnvalidated methods, such methods are used for updating, and like createUnvalidated methods, non-valid fields are allowed.
Finally, performance of GenericRESTService has been improved. Previously, validations were executed twice for each entity being imported due to previous limitations of IGenericDAO interface. Now, a new method has been added to IGenericDAO to make possible to execute validations only one time for each entity being imported.
2010-02-12 10:53:54 +01:00
Óscar González Fernández
c9ea9ea65d
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: Avoiding first day gives zero hours for splines interpolation.
...
For each day the accumulated hours are the hours accumulated until
that day included. Before this commit the hours of that day were not
included.
2010-02-11 22:07:00 +01:00
Óscar González Fernández
8a91e5a669
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #282 ] Fixing bug.
...
The problem lies in that the start and end data were retrieved from
allocation. Allocation start and end are calculated looking into day
assignments. The first day was assigned to zero hours when applying
the splines and this caused that the allocation start slipped to the
next day. As the first interval end was the task's next day too it
provoked the failure.
2010-02-11 22:07:00 +01:00
Susana Montes Pedreira
433e004ede
ItEr47S08RFNavegacionOrganizacionTraballoItEr46S09 : Load the advances of the current order on demand.
2010-02-11 20:16:53 +01:00
Susana Montes Pedreira
60b95b18e4
ItEr47S08RFNavegacionOrganizacionTraballoItEr46S09 : Load the assigned hours to the order on demand.
2010-02-11 20:16:51 +01:00
Susana Montes Pedreira
3de2358f77
ItEr47S08RFNavegacionOrganizacionTraballoItEr46S09 : Load the order elements tree on demand.
2010-02-11 20:07:14 +01:00
Óscar González Fernández
9bb66ed9e7
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #285 ] Fixing bug.
...
For TaskMilestones the order element is null, so the calendar can't be retrieved from there.
2010-02-11 14:39:47 +01:00
Lorenzo Tilve
15fcefa907
ItEr46S20CUAsignacionGrupoRecursosAPlanificacionItEr32S12: Added tooltiptext and resolved alignment problems in advanced allocation window details
2010-02-11 12:41:52 +01:00
Lorenzo Tilve
1150b02438
ItEr46S20CUAsignacionGrupoRecursosAPlanificacionItEr32S12: Fixed problems with timetracker horizontal scrolling after zoom changes
2010-02-11 12:30:36 +01:00
Lorenzo Tilve
6380ac9eef
ItEr46S20CUAsignacionGrupoRecursosAPlanificacionItEr32S12: Removed extra years in advanced assignment timetracker
2010-02-11 12:30:33 +01:00
Lorenzo Tilve
508c205220
ItEr47S16CUAsignacionGrupoRecursosAPlanificacionItEr46S20: Added icon to configure assignment function button
2010-02-11 12:30:30 +01:00
Susana Montes Pedreira
70156d687d
ItEr46S09RFNavegacionOrganizacionTraballoItEr45S09 : Optimization DateBox components in the OrderElement view.
2010-02-11 12:14:09 +01:00
Manuel Rego Casasnovas
90a056586a
ItEr47S17CUFiltradoNaPlanificacionItEr46S21: Added interface for multiple filter to order planning view.
2010-02-11 10:39:31 +01:00
Óscar González Fernández
51c4603ede
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #280 ] Fixing bug.
...
The hours were retrieved from the task instead of the ResourceAllocation
2010-02-10 21:37:40 +01:00
Óscar González Fernández
9ee62948ac
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #278 ] Fixing bug.
...
Avoiding changing the reference for derived allocations in order to avoid error.
2010-02-10 17:00:32 +01:00
Manuel Rego Casasnovas
80d23a85af
ItEr47S17CUFiltradoNaPlanificacionItEr46S21: Added button to expand and collapse all the task in the planning view.
2010-02-10 14:17:21 +01:00
Diego Pino Garcia
297c6b1cde
ItEr46S04ValidacionEProbasFuncionaisItEr45S04: [Bug #270 ] Delete Order launches an Exception
2010-02-10 14:10:19 +01:00
Óscar González Fernández
b839c67325
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #275 ] Fixing bug.
...
The problem was that planning tab was loaded using
LongOperationFeedback. This postpones the execution to an echo event,
causing a race condition: when entering goToOrderElementDetails the
planner could still not be loaded. Because of this it's not removed
and both the order detail and the planner appear.
2010-02-10 13:41:20 +01:00
Óscar González Fernández
305982a4f2
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #275 ] Avoiding name collision.
...
It was failing when the planner is directly loaded without LongOperationFeedback
2010-02-10 13:41:19 +01:00
Óscar González Fernández
eb39e4b887
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: Fix formatting
2010-02-10 13:41:19 +01:00
Fernando Bellas Permuy
22c883820a
ItEr47S12CUImportacionRecursosProductivosItEr46S13: ResourceServiceREST adapted to GenericRESTService and added support for recoverable errors.
...
ResourceServiceREST has been adapted to GenericRESTService. Updating functionality in ResourceServiceREST is not implemented yet.
As part of this patch, the generic infraestructure for REST services has been improved. In particular, recoverable error support has been provided. Exceptions representing recoverable errors must extend from RecoverableErrorException. To demonstrate this capability, ResourceServiceREST nows reports non-existent calendars, criterions, critetion types, and cost categories as recoverable errors.
2010-02-10 13:09:28 +01:00
Óscar González Fernández
de3adddecc
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #277 ] Fixing bug.
...
The task's calendar was not being forced to be loaded.
2010-02-10 10:46:39 +01:00
Óscar González Fernández
1f0d26516a
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: Formatting some bad formatted code
2010-02-10 10:37:00 +01:00
Óscar González Fernández
150eacae86
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #276 ] Adding prefixes with the name of the topmost task.
2010-02-09 21:44:33 +01:00
Óscar González Fernández
62a7eeaae6
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #276 ] Fixing bug.
...
Limiting the width and if the width is bigger a popup is shown.
2010-02-09 18:02:28 +01:00
Óscar González Fernández
89f21bb649
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: Increasing the width of the left pane for resources load
2010-02-09 18:02:28 +01:00
Óscar González Fernández
c39b28e1ce
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: Reattaching criterion to avoid LazyInitializationException.
...
The error only happens sometimes when it has satisfactions
2010-02-09 18:02:28 +01:00
Manuel Rego Casasnovas
69c15984a4
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #274 ] Fixing bug setting initial zoom level for charts.
2010-02-09 16:32:13 +01:00
Jacobo Aragunde Pérez
5b36d4ff69
ItEr46S11CUAsignarUsuarioAProxectoPlanificacionItEr45S09: Corrected bug: when authorizations changed and 'save & continue' was pressed, they weren't checked again.
2010-02-09 14:22:25 +01:00
Jacobo Aragunde Pérez
c6ef865968
ItEr46S22CUPasarPedidosAHistorico: Save buttons are disabled when order status is STORED, and re-enabled when changed.
2010-02-09 14:22:21 +01:00
Jacobo Aragunde Pérez
09b510f2b0
ItEr46S22CUPasarPedidosAHistorico: code rebase that will help in the implementation of this use case.
2010-02-09 14:22:18 +01:00
Jacobo Aragunde Pérez
5760b9509d
ItEr46S22CUPasarPedidosAHistorico: Created the new status 'stored' for orders.
2010-02-09 14:22:15 +01:00
Jose Maria Casanova Crespo
9a6c0726a7
ItEr47S06DocumentacionFormacionItEr46S06: Includes git ignore for development documentation
2010-02-09 13:56:27 +01:00
Jose Maria Casanova Crespo
53de47d954
ItEr47S06DocumentacionFormacionItEr46S06: Included images from the development guide
2010-02-09 13:56:27 +01:00
Jose Maria Casanova Crespo
81f5e7e588
ItEr47S06DocumentacionFormacionItEr46S06: Fix rst format problems in compilation
...
Modified format related to indentation and emphasis
2010-02-09 13:56:27 +01:00
Óscar González Fernández
c089051fdd
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: Simplifying call.
...
Providing the resource dao in the constructor
2010-02-09 12:56:41 +01:00
Óscar González Fernández
2ccf19bf24
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #272 ] Fixing bug.
...
Loading the criterions at PlanningState in order to avoid duplicated instances.
2010-02-09 12:49:28 +01:00
Óscar González Fernández
d580601ae7
ItEr47S04ValidacionEProbasFuncionaisItEr46S04: [Bug #271 ] Fixing bug.
...
Message changed to a more generic one. Updating i18n pending.
2010-02-09 11:15:19 +01:00
Óscar González Fernández
b194d5cbaf
ItEr47S11CUVisualizacionResponsabilidadesTRaballoNaPlanificacionItEr46S12: Fixing problem.
...
After a reload resources text, e.g. when moving a task, the resize
capability was lost. yui-resize css class must be added.
2010-02-08 23:48:25 +01:00
Óscar González Fernández
1f900917f7
ItEr47S11CUVisualizacionResponsabilidadesTRaballoNaPlanificacionItEr46S12: Updating width from wrapped task.
...
If the task can't be resized this would make it to get back to its original size
2010-02-08 23:37:09 +01:00
Óscar González Fernández
f1bbab882c
ItEr47S11CUVisualizacionResponsabilidadesTRaballoNaPlanificacionItEr46S12: When resizing a task it's reallocated if possible
2010-02-08 23:33:02 +01:00
Óscar González Fernández
106a3458a2
ItEr46S04ValidacionEProbasFuncionaisItEr45S04: Fixing problem.
...
When activating recommended allocation and the calculated value is not
resources per day it kept the previous resources per day value. Now it
is reset to zero.
2010-02-08 13:53:40 +01:00
Óscar González Fernández
a3ccebfbc3
ItEr46S04ValidacionEProbasFuncionaisItEr45S04: Fixing problem loading a scheduling with a milestone.
...
Working hours are only loaded if task source exists, e.g. it's not a milestone.
2010-02-08 11:36:55 +01:00
Óscar González Fernández
889027d2ea
ItEr46S04ValidacionEProbasFuncionaisItEr45S04: Fixing problem when moving a milestone.
...
Avoiding to show the resources text for a milestone since it doesn't
suppor it.
2010-02-08 11:20:35 +01:00
Óscar González Fernández
901a8300f1
ItEr46S04ValidacionEProbasFuncionaisItEr45S04: [Bug #269 ] Fixing bug.
...
The milestones dates were not being initialized. Now are forced to be initialized
2010-02-08 11:05:27 +01:00